Introduction
The Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-196/2016)
prepared for the “Tung Chung New Town Extension” (hereinafter referred to as “the Project”)
has been approved by the Director of Environmental Protection, and an Environmental Permit
(EP) (Permit No.: EP-519/2016) has been issued for the project under the Environmental
Impact Assessment Ordinance.
The submission of Management Organizations has been prepared in accordance with Condition
2
.11 of the EP, which includes the following information:
(
a)
the management organization of the main construction companies and/or any form of
joint ventures associated with the construction of the Project;
the management organization of the Environmental Team (ET); and
the management organization of the independent Environmental Checker (IEC) and the
supporting team.
(b)
c)
(
The development of Tung Chung New Town Extension (TCNTE), comprising Tung Chung
East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to
provide land to meet the future housing economic and social development needs of Hong Kong.
Due to the fact that the proposed works are geographically separated, the implementation of
mega-scale Project is divided into two packages, namely TCE and TCW respectively. In
accordance with the tight delivery programme, the Project will be implemented in phases under
separate contracts for the developments of TCE and TCW. This submission only covers the
This submission will be updated when there are any changes of the management organizations
for TCW.
2
.
Management Organization of the Main Construction Companies
2
.1
Contract No. NL/2020/05 – Tung Chung New Town Extension – Site Formation and
Infrastructure Works at Ma Wan Chung
Build King – Richwell Civil Joint Venture (BKRCJV) is the contractor appointed to undertake
the site formation and infrastructure works at Ma Wan Chung. Names of the responsible
persons and their contact details are set out in Table 1 below.
Table 1: Contact Information of the Main Construction Companies
Name
Eric Yip
Artie Wong
Position
Telephone
9196 6098
9633 0977
Project Manager
Construction
Manager
Ricky Hon
Andy Kwan
Calvin Chan
Site Agent
9100 7509
9400 9422
6117 2894
HSE Manager
Environmental
Officer
The organization chart of the main construction companies required under EP Condition 2.11
is given in Attachment I.